Budgets¶
Definition¶
The monetary budgets assigned to a specific iati-activity
can be described in the IATI activity standard using the following:
transaction-type
type Commitment (code 2) can be used to describe the total committed budget for the duration of the activity. Any changes to the original commitment should be reported as additional, incremental transactions (positive or negative) so that the sum of commitments represents the total committed budget.budget
- the value of theiati-activity
budget
for each financial year over the lifetime of the activity, as stated in the original project document or revised accordingly. The status explains whether the budget being reported is indicative or has been formally committed. The value should appear within the BudgetStatus codelist. If the @status attribute is not present, the budget is assumed to be indicative. The sum of budgets may or may not match the sum of commitments, depending on a publisher’s business model and legal frameworks.planned-disbursement
- a scheduled payment, set up against thebudget
Additionally, there are two areas within the IATI activity standard that allow further clarification of budgets:
country-budget-item
- alignment ofiati-activity
with the functional and administrative classifications used in therecipient-country
Chart of Accounts.capital-spend
- the percentage of the total commitment that is for capital spending.
These all relate to the specific iati-activity
being described.
Considerations¶
When using the IATI activity standard to declare budgets, the following should be considered:
It is recommended that budgets are presented in financial years.
A budget must not span a period greater than one year.
When presenting multiple budgets, then the
budget
element should be repeated accordingly.It is expected that the financial years for
reporting-org
are described.It is possible to report periods other than years, but this is not recommended.
Financial periods can be presented using the
period-start
andperiod-end
dates.For
planned-disbursement
it is valid to only report theperiod-start
as a single date.It is possible to report budget values in multiple currencies, overriding the default currency set in
iati-activity
It is expected that budgets would be described from the
reporting-org
perspective.When declaring a
value-date
for any budget, this date must be in the past.
2.01+ Considerations¶
In versions 2.01 and above, the following must also be considered:
The
planned-disbursement
element no longer has an@updated
attribute. This has been replaced by a@type
attribute